CareerExamPro

NCEES PE Mechanical (HVAC/Thermal) & Electrical Power Exam practice test

7 practice questions for this exam, each with a full explanation and cited rule or blueprint reference.

Start practising

CA Seismic, NCEES PE/SE & BGC CIH: practice drill

10 realistic exam questions, graded as you go, with the exact rule or statute citation for every answer. Start free, no sign-up.

Practice tests that prepare you for this exam

Practise by topic

About this exam

Agency / Issuer
NCEES
Region
United States

Exact question counts, passing scores, and allowed reference materials vary by testing window and state/agency. Always confirm current rules with the official testing provider.

Sample questions

A sea-level commercial air-handling unit delivers 12,000 CFM of conditioned supply air to maintain an office zone at 75.0°F dry-bulb. The zone design cooling load consists of 233,280 BTU/hr sensible heat and 60,000 BTU/hr latent heat. Using the standard sensible air heat-transfer equation (q_s = 1.08 * CFM * delta_T), what are the required supply air dry-bulb temperature and the total coil cooling capacity in tons?

  1. Supply air = 52.4°F and total cooling = 24.4 tons, inserting the combined sensible plus latent load into the 1.08 equation.
  2. Supply air = 57.0°F and total cooling = 19.4 tons, because latent moisture removal does not add to mechanical refrigeration tonnage.
  3. Supply air = 61.5°F and total cooling = 24.4 tons, because the sensible constant 1.08 applies only to heating coils.
  4. Supply air = 57.0°F and total cooling = 24.4 tons, using only sensible load for delta_T and total load for tonnage.
Show the answer

D. Supply air = 57.0°F and total cooling = 24.4 tons, using only sensible load for delta_T and total load for tonnage.

Supply-to-room dry-bulb temperature difference is governed strictly by sensible heat: delta_T = q_s / (1.08 * CFM) = 233,280 / (1.08 * 12,000) = 233,280 / 12,960 = 18.0°F, requiring a supply air temperature of 75.0 - 18.0 = 57.0°F. Total refrigeration capacity must remove both sensible and latent loads: Q_total = (233,280 + 60,000) / 12,000 = 293,280 / 12,000 = 24.44 tons (24.4 tons).

Reference: ASHRAE Handbook—Fundamentals / NCEES PE Mechanical Reference Handbook (HVAC Sensible & Total Cooling Load)

A balanced three-phase, 480 V (line-to-line) industrial induction motor draws 125 A per phase at a lagging power factor of 0.80 and operates at 92% mechanical efficiency (1 HP = 0.7457 kW). What are the motor's apparent power (S), electrical real power input (P_in), and mechanical shaft output (HP)?

  1. S = 60.0 kVA, P_in = 48.0 kW, and output = 59.2 HP, omitting the sqrt(3) factor from V_L * I_L.
  2. S = 103.9 kVA, P_in = 83.1 kW, and output = 121.2 HP, dividing input power by 0.92 efficiency.
  3. S = 103.9 kVA, P_in = 83.1 kW, and output = 102.6 HP, applying sqrt(3), PF = 0.80, and 92% efficiency.
  4. S = 103.9 kVA, P_in = 103.9 kW, and output = 128.2 HP, applying efficiency directly to kVA without power factor.
Show the answer

C. S = 103.9 kVA, P_in = 83.1 kW, and output = 102.6 HP, applying sqrt(3), PF = 0.80, and 92% efficiency.

For a balanced three-phase load, apparent power is S = sqrt(3) * V_L * I_L = 1.7321 * 480 * 125 / 1,000 = 103.92 kVA. Real electrical input power is P_in = S * PF = 103.92 * 0.80 = 83.14 kW. Accounting for 92% efficiency, mechanical shaft output is P_out = 0.92 * 83.14 = 76.49 kW, which converts to 76.49 / 0.7457 = 102.6 HP.

Reference: NCEES PE Electrical and Computer: Power Reference Handbook (Balanced Three-Phase Power & Motor Efficiency)

Taking this exam soon?

Tell us which exam domains or calculation drills you want more practice on.

Other PE Civil, CA Seismic & CIH exams